Provided technical support to vessel Owners, in connection
with general repairs, modifications and structural rectification work carried out whilst the
vessel was in drydock and subsequently afloat. Work carried out by A
Adamson & Co personnel included:-
-
Conducting
as-built surveys of vessel structure to identify deficiencies,
preparation of repair specifications based on findings and supervision of
remedial work.
-
Supervision of structural rectification of topside stools and other
load- bearing structures including turret, drag chain tower and crane foundations.
-
Overseeing
various structural work elements, including fatigue
mitigation and hull reinforcement, liasing with DNV Classification and Engineering
contractors on issues raised in the course of construction.
-
Co-ordinating
repair of GRE ballast system, comprising pipework renewal, pipe
support upgrading and eventual hydrostatic test.
-
Supervising
upgrading and improvement of materials handling and lifting
arrangements throughout vessel, and co-ordination of load testing and
certification.
-
Repair, mechanical completion
and commissioning of marine piping systems, fire
doors and accommodation space closures.
-
Overseeing miscellaneous repair work in connection with safety and
operational issues, and verifying compliance with requirements of various
regulatory authorities (DNV, NMD, NPD).
Back
to Top |
|
Performed
structural surveys of vessel hull whilst afloat, and produced detailed
reports with recommendations. Based on survey findings, developed and
produced repair specification, and supervised steelwork repairs.
Subsequently
provided technical services to Life Extension Project Team,
specifically in relation to expediting completion of Special Survey and
related repair activities. This included planning and completing survey of
tanks or specific areas to achieve class acceptance of same, thus
progressing close-out with minimal delay. Surveys were arranged to suit
programmed repair activities, and comprised close-up inspection from
available stagings or by rope access means. Special Survey was completed
on-schedule, in November 2001.
Back
to Top
|